August Update

1 August 2017

Retention works on site are progressing well, with the piling now complete and capping beam pours set to be completed by early August. Bulk excavation is underway and scheduled to be completed by mid-October.

The WEBS program is also inviting an artist to reappropriate reclaimed timber as a result of building works adjacent to the System Garden. Submissions for works will be based on a positive vision and underpinned by the principles of the University of Melbourne’s System Garden, exploring ideas and notions around education and learning in the field of plant research and the biosciences.